SIEMAG Production Report · shift active
LIVE
5,863 short tons hoisted today
3% ahead of pace
518
skips today
92%
hoist availability
5
faults today
0
live updates today · the morning PDF: one
Current Time: | Report Date: June 1, 2026
Siemag Tecberg

SIEMAG Production Report


June 1, 2026
Aweeba

Daily Production

3% ahead of pace vs target
MT 5,318
83.75%
Skips 518
Hours 16:37:48

Record Day (Year)

Fiscal Year Date Tons
FY 2026 May 4, 2026 9,623
FY 2025 N/A 0

Record Week (Year)

Fiscal Year Week Ending Tons
FY 2026 May 24, 2026 55,506
FY 2025 N/A 0

Hoist Availability

Mode - Off 01:50:00
Mode - Skip Auto 20:59:59
Mode - Skip Manual 00:00:00
Waiting - Surge Bin Full 00:00:00
Waiting - Loading Pocket South 00:00:00
Waiting - Loading Pocket North 00:00:00
Hoist Faulted CAT1, CAT2 01:30:00
E-Stop 00:20:00
Mode - Inspect 00:00:00
Mode - Personnel 01:00:00
Mode - Rope Up 00:00:00
Mode - Heavy 00:00:00
Mode - Gravity 00:00:00
Mode - Brake Maintenance 00:10:00
Single Skip North Side 03:40:00
Single Skip South Side 03:00:00
Tipple Bin North High 00:40:00
Tipple Bin North Off 00:00:00
Tipple Bin South High 01:00:00
Tipple Bin South Off 00:00:00
Faults Summary
4 Faults
Code Description Category Occurrences Duration
233 Skip Overload Load 2 00:30:00
134 Medium Voltage Transformer Tripped Drive 1 00:20:00
170 Drive Communications Drive 1 00:20:00
212 Loading Pocket Not Ready Position 1 00:20:00

05/31/2026 | 1st Shift - 11:00 PM to 6:59 AM

Start End Skips North Skips South Skips Hour MT North AVG MT North MT South AVG MT South Total MT AVG Total MT Total ST Hourly Target | 400
23:00 00:00 19 20 39 197 10.39 203 10.20 401 10.29 442 100.3%
00:00 01:00 15 23 38 162 10.83 234 10.20 397 10.45 437 99.3%
01:00 02:00 18 21 39 186 10.38 213 10.19 400 10.28 441 100.0%
02:00 03:00 19 19 38 195 10.28 196 10.32 391 10.30 431 97.8%
03:00 04:00 19 19 38 189 9.97 196 10.35 386 10.16 425 96.5%
04:00 05:00 0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
05:00 06:00 14 22 36 145 10.36 226 10.27 371 10.31 409 92.8%
06:00 07:00 0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
Totals: 104 124 228 1,076 10.35 1,271 10.25 2,347 10.30 2,588 73.3%

06/01/2026 | 2nd Shift - 7:00 AM to 2:59 PM

Start End Skips North Skips South Skips Hour MT North AVG MT North MT South AVG MT South Total MT AVG Total MT Total ST Hourly Target | 400
07:00 08:00 17 21 38 179 10.54 214 10.22 393 10.36 434 98.3%
08:00 09:00 18 21 39 177 9.85 208 9.95 386 9.90 425 96.5%
09:00 10:00 17 18 35 172 10.16 184 10.26 357 10.21 393 89.3%
10:00 11:00 23 15 38 239 10.42 154 10.29 394 10.37 434 98.5%
11:00 12:00 0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
12:00 13:00 18 21 39 189 10.55 210 10.02 400 10.27 441 100.0%
13:00 14:00 19 21 40 190 10.00 215 10.26 405 10.14 447 101.3%
14:00 15:00 21 15 36 221 10.55 149 10.00 371 10.32 409 92.8%
Totals: 133 132 265 1,370 10.31 1,338 10.14 2,709 10.22 2,986 84.7%

06/01/2026 | 3rd Shift - 3:00 PM to 10:59 PM

Start End Skips North Skips South Skips Hour MT North AVG MT North MT South AVG MT South Total MT AVG Total MT Total ST Hourly Target | 400
15:00 16:00 10 15 25 107 10.77 153 10.25 261 10.46 288 65.3%
16:00 17:00 0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
17:00 18:00 0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
18:00 19:00 0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
19:00 20:00 0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
20:00 21:00 0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
21:00 22:00 0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
22:00 23:00 0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0%
Totals: 10 15 25 107 10.77 153 10.25 261 10.46 288 8.2%
1st Shift - MIDS

2,587 ST

2nd Shift - DAYS

2,986 ST

3rd Shift - AFTS

287 ST

Daily Production Progress
5,862 ST Target: 7,000.00 ST
83.75%
On track - good progress

Filter Faults

Default: Last 7 days
Leave empty for all faults

Top 10 Faults by Duration

Loading Top 10 faults...

All Faults

0 Faults
Code Mode Description Category Timestamp Duration

Faults by Occurrence

0 Faults

Loading faults by occurrence...


Shift Intelligence
June 1, 2026 Current Shift
Shift Summary

The shift produced 5318.38 tons across 518 skips, falling short of the 7000-ton daily target by 1681.62 tons (76% of goal). The team experienced 4 fault events (1 Load, 2 Drive, 1 Position) totaling 90 minutes of downtime and 2 E-stop events totaling 0 minutes.

Operational Impact
  • Produced 1681.62 tons below daily goal (24% shortfall), putting monthly target at risk
  • 90 minutes of fault-related downtime reduced potential output by approximately 144 tons
  • Year-to-date production at 10% of annual target - sustained improvement needed to meet yearly goals
Priority Focus
  1. Production significantly below target - conduct shift debrief to identify systemic issues
Quick View
Daily Target
76%
Top Fault
Code 233 (2x)
Fault Downtime
90 min
E-Stops
2 events
Operating Hours
16.6 hrs

Shift Performance Trends
Shift 1
↘️ 83%
Actual 2,347 tons
Pace 391.2 tons/hr
Projected 3,129 tons
Target 3,760 tons
Shift 2
↘️ 82%
Actual 2,709 tons
Pace 387.0 tons/hr
Projected 3,096 tons
Target 3,760 tons
Shift 3
↘️ 56%
Actual 261 tons
Pace 261.0 tons/hr
Projected 2,088 tons
Target 3,760 tons
s